Here is an update on the Fire station building program.

Two of our stations, Wattamondara and Chaucer in the Cowra Local Government Area are near completion.

Wattamondara

Wattamondara

Chaucer

Chaucer

Mandurama in Blayney LGA is ready to paint and then complete fit out.

Mandurama

Mandurama

Orange City LGA  - Spring Hill is to lock up with plumbing and electrical rough-in commencing. Clifton Grove Ophir is being clad  and should be to lock up by the end of the week.

Spring Hill 1

Spring Hill

Spring Hill 2

Spring Hill

Clifton Grove Ophir

Clifton Grove Ophir 

Cabonne LGA - Moorbel slab is down and erection will commence late this week. Lidster site works completed and slab to go down mid March.

Moorbel